Gas sampling and gas conditioning technology 10-1.1.1-ME
13 INITIAL OPERATION
Prior to initial operation, the system and process-specific safety measures must be observed !
The following steps must be carried out prior to initial operation:
Prior to initial operation, compare the system voltage with the voltage shown on the rating plate;
Connect the air conditioning unit to the mains;
Connect status contact ouput, if necessary ;
Operate the “Power/On” switch (green LED lights).
Check the nominal temperature of 500°C at the temperature controller (see Figure 2).
When operational readiness has been reached (about 15 minutes), the 1 lights upin the display.
The air conditioning unit is operated with min. 73 psi and max.
145 psi inlet pressure.
The maximum gas flow is 15Nl/min.
14 SWITCH OFF
The place of installation of the air conditioning unit must be
remain free from frost also during time when the unit is switched
off !
Switch off the device and disconnect the pressure air.
No more particular measures are required for switch off.
15 MAINTENANCE
Before carrying out maintenance work, the system and process-specific safety measures must be
observed!
The air conditioning is operated with max. 145 psi inlet pressure.
High voltage and high pressure. Disconnect the mains plug and
the pressure air inlet before opening the housing!